Clay County, FL
Home MenuRoad Projects
You can get the latest information on the road projects that are ongoing or planned in our county right at your fingertips every week! Sign up for our road and lane closure report, which comes directly to your email every Friday.
If you have any questions about our county road projects, please email askclay@claycountygov.com.
For the latest FDOT project updates in Clay County, please visit the FDOT Northeast Florida Roads website
The weekly FDOT District Two - Northeast Florida Road and Lane Closure Report is posted each Friday afternoon.
Major Road Projects List
We update these projects as new information becomes available, which can be frequent, depending on the project.
Click on the road name for more information on each project and monthly updates.These projects are anticipated to start in the upcoming weeks. Please note that details can change, so please check back for updates.
County Road 209 Riverside resurfacing (Green Cove Springs)- Crews anticipate beginning a milling and resurfacing project on County Road 209 Riverside from US 17 to Ivey Lane in late February to early March. Anticipate daytime, single-lane closures once work begins. The project could take up to 3 weeks to complete.
County Road 220 and Town Center Boulevard Resurfacing from US 17 to west of Brookstone Drive (Fleming Island) — Crews will begin resurfacing County Road 220 from U.S. 17 to Arena Road in late February to early March. Drivers should expect nighttime lane closures and traffic shifts during construction. Work could take up to three weeks to complete.
Doctors Lake Drive resurfacing (Fleming Island/ Orange Park) – Crews will begin a milling and resurfacing project on Doctors Lake Drive from Peoria Road to Kingsley Avenue in early 2026. We will provide updated start dates as soon as plans are finalized.
Old Jennings Road/ Long Bay Road new traffic signal and intersection improvements (Middleburg) – Crews will soon begin installing a new traffic signal and making improvements at the intersection of Old Jennings Road and Long Bay Road in Middleburg. Work is anticipated to begin in early March.
Choctaw Trail sidewalk installation (Middleburg) – Install a new five-foot-wide, 2,000-foot sidewalk with two ADA ramps along Choctaw Trail in Middleburg from Chief Ridaught Trail to Apalachicola Boulevard. Anticipate daytime single-lane closures and lane shifts. Work began January 26 at Harrison Avenue and Logan Street (30 days), with the next section on Choctaw Trail starting February 27 for an additional 30 days.
Evergreen Lane sidewalk installation (Lakeside/Middleburg) – Construction began the week of December 2 near Doctor’s Inlet Elementary School as part of the Safe Routes to School program. The project will expand sidewalk connectivity along several nearby streets to improve pedestrian and bicycle safety and help reduce school traffic. Drivers should expect intermittent daytime single-lane closures and traffic shifts during construction.
Jefferson Avenue sidewalk replacement (Orange Park) - Intermittent daily lane closures and a full sidewalk closure on Jefferson Avenue started June 3. Crews are replacing the sidewalk on Jefferson Avenue between Harrison Avenue and Washington Avenue. We will update this notice when the work is finished.
County Road 209 (Russell Road) from Peters Creek Bridge to US 17, Bonded Transportation Program Project #2 (Lake Asbury)
Background
This project includes the design and reconstruction of the two-lane roadway into four lanes with a median, turn lanes, bike lanes, curb and gutter, and sidewalks on County Road 209 from County Road 315B to US 17, and from County Road 315 to south of Peters Creek Bridge. Drivers can expect single-lane closures and anticipate delays and weekend work. All work is estimated to be completed in Spring 2027. Please slow down and use caution around the crews working close to the roadway.
- Nighttime road work notice This project may involve nighttime construction activities to reduce daytime disruptions and complete the work faster. Residents in the area can expect increased noise levels or vibrations from machinery, as well as potential glare from temporary work lights near the site. We appreciate your understanding and patience during this time. Our team will make every effort to minimize inconvenience and complete the work as quickly and safely as possible.
Latest updates
- Update February 10, 2026 — East of the railroad tracks, traffic continued to flow along the north side of CR 209 while crews continued work on the sub-base and base material, as well as storm-drain pipe installation, on the south side of the roadway. West of the railroad tracks, traffic was shifted to the newly paved southbound outside lane. The project remains on schedule.
Previous updates
- Update January 13, 2026 — Traffic continues to flow on the north side of CR 209 east of the railroad tracks while crews install sub-base and base materials, storm drainage, curb, and sidewalk on the south side. Traffic patterns were recently adjusted, opening up the intersections at CR209 and CR315B, as well as the railroad tracks. A traffic shift west of the railroad tracks moved southbound vehicles onto new asphalt on CR 315B and CR 209.
- Update December 9, 2025 — East of the railroad tracks, traffic continued to flow on the north side of CR 209 while crews installed sub-base and base material, storm-drain pipe, curbing, and sidewalk along the south side of this section. Crews also completed installation of storm-drain pipes and structures, as well as sidewalk and curbing, and placed the initial lift of asphalt along Russell Road, north of and at the CR 315B intersection. A traffic switch is anticipated during the week of December 8, shifting traffic onto the newly paved sections of CR 315B and CR 209 west of the railroad.
- Update December 2, 2025- Beginning December 10, traffic will be shifted onto the new pavement on CR 315B approaching the signalized intersection at Russel Road. Traffic will also be shifted onto new pavement on CR 209 between the railroad crossing and Peters Creek. Drivers should expect flagging operations and some delays during the traffic shift.
- Update November 10, 2025- Traffic continued flowing on the North side, east of the railroad tracks, while crews continued the installation of sub-base & base material, installation of storm-drain pipe, as well as installation of curbing and sidewalk on the south side of this section of road. Crews also continued installing the storm-drain pipe and structures along with sidewalk and curbing along Russell Road, north of the CR315B intersection. A traffic switch is anticipated for early to mid-December. This project is on schedule for completion.
- Update October 14, 2025- Traffic continued flowing on the North side, east of the railroad tracks, while crews continued the removal of the old asphalt roadway on the south side of this section of road. Crews also continued installing the storm-drain pipe along Russell Road, north of the CR315B intersection. A traffic switch is anticipated for December 10th (Phase 3 west of the RR tracks – work zone in the median). This project is on schedule for completion.
- Update September 9, 2025- With traffic now shifted to the north side of the east-west section of the project, crews have begun removing the old asphalt from the south side of this roadway segment. Crews are also installing storm drain pipes along Russell Road, north of the CR315B intersection.
- Starting September 30, the Russell Road (CR209) entrance to the RaceTrac gas station at US 17 and Russell Road will be closed for approximately eight months. Drivers will need to use the access off US Hwy 17.
- Update August 12, 2025- Cross-drain installation at Pond 2, along with embankment and base material placement between the railroad tracks and Pond 2, has been completed. Base course pavement has been placed on the north side of CR 209, and traffic has been shifted to this newly constructed section. Crews are continuing to install stormwater drainpipes, sidewalks, and curbing along the north side of the roadway.
-
On Saturday, August 2, there will be a one-day road closure and detour on County Road 209 from Russell Road to US 17, from 7:30 AM to 5 PM, for a construction phase switch. Drivers will be detoured along County Road 315B and County Road 315.
- Update July 8, 2025- Crews are currently installing stormwater drainpipes and curbing along the north side of County Road 209. Cross-drain installation at Pond Site 2 has been completed, and work is now progressing on the embankment and base between the railroad tracks and Pond Site 2. Upcoming tasks at Pond Site 2 include installing cut-off walls and completing the final grading. Weather permitting, final pavement on the north side of County Road 209 is scheduled for the week of July 21.
-
Update July 3, 2025- Anticipate a traffic shift on County Road 209 beginning July 12 for neighborhood access road work. The dedicated eastbound left turn lane into the Edgewater Landing neighborhood will be temporarily removed. Vehicles will still be able to turn left into the neighborhood from the through travel lane. Work will take approximately two weeks to complete.
- June 10, 2025- The project remains on schedule for completion. Crews are installing stormwater pipes on the north side of the road and backfilling over the pipes. The removal of unsuitable materials continues along with the placing of base materials and limestone for the final pavement work.
- May 15, 2025- Stormwater drainpipe installation continues on the north side of CR209, along with backfilling over the pipes. Crews are also removing unsuitable materials and placing base materials and limestone in preparation for final paving. The project remains on schedule. Drivers can expect delays and weekend work as well.
- May 8, 2025- Beginning May 5th, drivers can expect single-lane closures on Russell Road for drainage and utility work. Drivers can expect delays and weekend work as well.
- April 11, 2025- Crews are continuing stormwater installation on the north side of County Road 209 and continue backfilling over the piles, placing base materials, and final pavement. A traffic shift onto the new temporary pavement is also in place.
- March 14, 2025- Work on County Road 209 from Peters Creek Bridge to US 17 is continuing with stormwater drainpipe installation on the north side of the road, and backfilling over pipes in preparation for base work and the final pavement application has begun. Crews are also placing temporary fill in preparation for temporary pavement on the south side of CR 209 and milling the southbound lanes of Russell Road.
- February 14, 2025- Work on County Road 209 from Peters Creek Bridge to US 17 is continuing with the placement of stormwater drainpipes between the railroad crossing and US 17, installing the final asphalt and curbing on County Road 209 at the railroad crossing, and placing temporary asphalt on Russell Road.
- January 5, 2025- The road closure and detour on County Road 209 at the CSX railroad tracks have been removed and the newly configured railroad track crossing is open to traffic. The temporary traffic signal and turn lane will remain in place at the intersection of County Road 315 and 315B. Please slow down and drive with caution in this area.
- November 26, 2024- CSX will finish their work on the railroad crossing by December 7 and the contractor will continue the CSX area upgrades and start paving on December 9. Electrical work on the final signal pole and the intersection signal work is anticipated to be completed and inspected by January 13. Crews are set to end the detour and move to the next phase on January 15.
- October 10, 2024- A road closure and detour began on September 9 on County Road 209 at the CSX railroad tracks to adjust the road profile to accommodate wider travel lanes. Local traffic ONLY- residents will have full access to their property during the work. Through traffic will be detoured 1.5 miles along County Road 315 and County Road 315B back to County Road US Highway 17. A temporary traffic signal and turn lane will be in place at the intersection of County Road 315 and 315B. Expect heavy delays and choose an alternate route if possible.
- August 15, 2024- Crews began reconstruction work to establish a new turn lane and traffic signal at the intersection of County Road 315 and County Road 315B the week of August 5. Crews will be resurfacing the roadway around this intersection September 2-8. Anticipate daily, intermittent lane closures beginning at 9:30 am for approximately six weeks. Watch for flaggers.
- August 9, 2024- A road closure and detour begins September 9 on County Road 209 at the CSX railroad tracks to adjust the road profile to accommodate wider travel lanes. Local traffic ONLY- residents will have full access to their property during the work. Through traffic will be detoured 1.5 miles along County Road 315 and County Road 315B back to US Hwy 17. A temporary traffic signal and turn lane will be in place at the intersection of County Road 315 and 315B. Expect heavy delays and choose an alternate route if possible. Work is anticipated to take up to eight weeks to complete.
- August 2, 2024- Crews will begin reconstruction work to establish a new turn lane at the intersection of County Road 315 and County Road 315B the week of August 5. Anticipate daily, intermittent lane closures for the next six weeks. Lane closures will begin at 7 a.m. prior to the start of school and at 9:30 a.m. once school is back in session.
- July 10, 2024- There will be a one-day westbound traffic detour on County Road 209 from US 17 to Revels Road on Saturday, July 20 from 7 a.m. to 4 p.m. During construction, drivers will be detoured on County Road 315.
- June 27, 2024- Anticipate intermittent, single-lane closures daily from 7 a.m. to 5:30 p.m. from U.S. Hwy 17 to Peters Creek Bridge for road work.
- June 21, 2024-There will be a one-day westbound traffic detour on County Road 209 from US 17 to Revels Road on Saturday, June 29. During construction, drivers will be detoured on County Road 315 to the south.
- June 11, 2024- Anticipate daily, single-lane closures from 7 a.m. to 5:30 p.m. on the east side of County Road 209 from the railroad tracks to Peters Creek Bridge beginning June 19. Work will take about two weeks to complete.
- May 31, 2024- There will be a one-day westbound traffic detour on County Road 209 from US 17 to Revels Road on Saturday, June 22. Drivers will be detoured on County Road 315 to the south while crews set up for drainage system installation.
- May 3, 2024- Construction begins on May 13th with drainage pipe installation throughout the project area. Anticipate daily, single-lane closures and watch for flaggers. Please slow down and use caution around the crews working close to the roadway.
- March 28, 2024- Anticipate daily intermittent, single-lane closures on County Road 209 between the railroad tracks and U.S. 17 for road work. Watch for flaggers. Drivers can also expect trucks entering and exiting the roadway.
- February 27, 2024- Preliminary clearing and grubbing work on the west side of Russell Road begins on March 1 and continues the week of March 4th. Anticipate temporary lane closures from 9 a.m. to 3 p.m. on Russell Road at the intersection of County Road 315 and going northbound. Watch for flaggers.
- January 30, 2024- Preliminary work to install drainage structures and for clearing and grubbing operations begins on February 12. No lane closures will be in place, but motorists can expect trucks entering and leaving the roadway.
- January 5, 2024 - Pond construction and clearing is anticipated to begin in mid-January and motorists can expect single-lane closures and flagging operations once work begins.
- December 15, 2023- Construction is anticipated to begin in early to mid-January and motorists can expect single-lane closures and flagging operations once work begins. Trucks and equipment will also be entering and exiting the work site.
- December 1, 2023 - Land clearing is anticipated to begin in early January and motorists can expect trucks and equipment entering and exiting the work site.
- November 17, 2023- Utility relocation work may begin as early as November 2023, with roadway construction beginning in January 2024.
County Road 209 (Russell Road) from Sandridge Road to Peters Creek Bridge, Bonded Transportation Program project #3, A & B (Lake Asbury)
Background
Project 3A includes the completed operational improvements at the intersections of Oak Stream Drive and County Road 209 and Watkins Road and County Road 209, including sidewalk installation.
Project 3B includes the widening and realignment of the east end of Sandridge Road (CR739B) with County Road 209B and operational improvements at the intersection of County Road 209 and County Road 209 B. All work is anticipated to be completed in the fall of 2025. Motorists should expect a 25 mph low-speed zone and overnight single-lane closures from 5:30 PM to 5:30 AM in the work zone. Please slow down and use caution around the crews working close to the roadway.
- Nighttime road work notice This project may involve nighttime construction activities to reduce daytime disruptions and complete the work faster. Residents in the area can expect increased noise levels or vibrations from machinery, as well as potential glare from temporary work lights near the site. We appreciate your understanding and patience during this time. Our team will make every effort to minimize inconvenience and complete the work as quickly and safely as possible.
Latest updates:
- Update February 12, 2026: TRAFFIC ALERT on Russell Road / Sandridge Road- Construction to tie in Russell Road and Sandridge Road began last weekend. The first phase will open the traffic circle for northbound and southbound traffic and provide access to CR 209B. Upcoming phases will include multiple traffic shifts, with flaggers directing traffic and patterns potentially changing daily. Expect delays. Work will occur during daytime and nighttime hours. Please use caution as crews work near traffic. The full transition to the new design is expected by March 7.
- Update February 10, 2026- (3B phase of Project 3 connecting the east end of project #4 on Sandridge Road and runs through the roundabout to CR 209B). Crews continued the installation of stormwater structures and pipes, curbing, sub-base, and base material in the roundabout area while placing sod and fencing around the Sandridge Road pond site.
Previous Updates:
- Update February 3, 2026: TRAFFIC ALERT on Russell Rd. / Sandridge Rd. The Sandridge Road entrance to Anabelle Island will be closed starting this weekend. All traffic must use the Russell Road entrance/exit for the next several weeks. Eastbound and westbound traffic on Sandridge Road will NOT use the Russell/Sandridge intersection. All traffic will be diverted to the new roadway. Drivers can expect single-lane traffic with flaggers and intermittent stops. Expect delays and heavy congestion — use an alternate route if possible. Crews will be working day and night. Plan ahead, leave extra time, and drive carefully through the work zone.
- Project Update – January 15, 2026 (Project 3, Phase 3B: Connecting the east end of Project #4 on Sandridge Road through the roundabout to CR 209B)- Beginning January 15 at 6 pm, 24-hour construction will start at the traffic circle and surrounding areas on Russell Road and CR 209B. Anticipate lane closures and flagging operations for several days. Immediately following, crews will begin work on Russell Road. This second phase will involve 24-hour operations with flagmen and single-lane traffic for several days while roadway work is completed. The third phase will focus on the traffic circle and is anticipated to last approximately 60 days. Intermittent lane closures are expected during this phase, though specific schedules are not yet available. Motorists should expect delays and slow traffic throughout the project, and alternate routes are recommended when possible. Please use caution, as workers will be operating near active traffic.
- Update December 11, 2025 (Project 3B) The entrance and exit lanes to the Anabelle Island subdivision off Sandridge Road will be closed for construction from January 19 – 26, 2026. All traffic will need to use the Russell Road entrance/exit.
-
Update January 13, 2026- (3B phase of Project 3 connecting the east end of project #4 on Sandridge Road and runs through the roundabout to CR 209B). Crews are continuing work along the corridor, installing stormwater structures and pipes, sub-base, and base materials. Sub-base, base, and curbing have been placed in the roundabout, and sidewalk construction is ongoing along the east side of Russell Road.
- Update December 9, 2025- (3B phase of Project 3 Connecting the east-end of project #4 on Sandridge Road and runs through the roundabout to CR 209B). Crews continued installing stormwater structures and pipes, as well as sub-base and base material throughout the corridor. Asphalt was placed along the Sandridge section, allowing traffic to shift to the outer lanes while work progresses in the interior median. Sub-base, base material, and curbing were installed in the roundabout area, and sidewalk construction is underway along the east side of Russell Road.
- Update November 10, 2025- (3B phase of Project 3 Connecting the east-end of project #4 on Sandridge Road and runs through the roundabout to CR 209B). Crews performed most of their work during night shifts, continuing the installation of stormwater structures and pipes.
- Update November 7, 2025- Anticipate a traffic switch on Sandridge road on Saturday November 8. at 7 AM. Drivers should pay attention to the signage in place. This switch will be in place until further notice.
-
Update October 23, 2025 (3B phase of Project 3 Connecting the east-end of project #4 on Sandridge Road and runs through the roundabout to CR 209B).
-
Upcoming Construction Notice – Anabelle Island & Cross Creek Subdivisions: Beginning October 23 and continuing through November 5, 2025, crews will begin excavation and installation of the asphalt base and structure in front of the Anabelle Island and Cross Creek subdivisions. Both Sandridge entrances will remain open throughout the project; however, traffic will be reduced to a single lane and managed by flaggers. Residents and emergency services will have full access at all times. Please expect delays in the area. To avoid congestion, we recommend using the Russell Road entrances during construction.
- Beginning November 3, crews will install sidewalk and curbing on Russell Road from Oak Stream Drive north to just past Sandridge Road. Anticipate daily lane closures with flaggers. Please slow down and use caution around the crews working close to the roadway.
-
Update October 14, 2025 (3B phase of Project 3 Connecting the east-end of project #4 on Sandridge Road and runs through the roundabout to CR 209B). Crews are working primarily at night to complete the installation of stormwater structures and pipes.
- Beginning October 6 at 5:00 P.M. and through the rest of the month, crews are doing nighttime paving operations on Sandridge and Russell roads. There will be lane closures and flaggers. Please slow down and be cautious.
- Update October 2, 2025 (3B phase of Project 3 Connecting the east-end of project #4 on Sandridge Road and runs through the roundabout to CR 209B). Crews are working primarily at night to complete the installation of stormwater structures and pipes.
- Update August 12, 2025 (3B phase of Project 3)- CCUA has completed the reclaim and water line relocation work, and crews are continuing with the installation of stormwater structures and pipes. Anticipate delays for day and evening lane closures as crews work to install underground pipe crossings on Russell Road near the new roundabout at 209 and 209B and on the east end of Sandridge Road between Robinson Ranch and Annabelle subdivisions.
- Update July 8, 2025 (3B phase of Project 3)- The project schedule has been updated due to the extended delay in permitting. CCUA has completed the reclaim and water line relocation work, and crews are continuing with the installation of stormwater structures and pipes. Anticipate delays for day and evening lane closures as crews work to install underground pipe crossings on Russell Road near the new roundabout at 209 and 209B and on Sandridge Road between Robinson Ranch and Annabelle subdivisions. Choose an alternate route if possible.
- June 10, 2025 (3B phase of Project 3)- Crews continue the installation of stormwater structures and pipes, and CCUA water main and reclaim utility relocation work is ongoing. The project schedule has been adjusted to account for the permitting delay.
- May 15, 2025- 3B phase of Project 3- Anticipate delays for day and evening lane closures beginning March 17th, and continuing for several weeks as crews work to install underground pipe crossings on Russell Road near the new roundabout at 209 and 209B and on Sandridge Road between Robinson Ranch and Annabelle subdivisions. Choose an alternate route if possible.
- March 14, 2025- Ongoing work on the 3B phase of Project 3 from Robinson Ranch Road to the new roundabout intersection with County Road 209B includes clearing and grubbing for the roadway and pond sites and installing stormwater structures and drainpipes. Anticipate delays for day and evening lane closures beginning Monday, March 17th, and continuing for several weeks as crews work to install underground pipe crossings on Russell Road near the new roundabout at 209 and 209B and on Sandridge Road between Robinson Ranch and Annabelle subdivisions. Choose an alternate route if possible.
- March 7, 2025- Work on the 3A phase of this project is complete, which included operational improvements at the intersections with Oak Stream Drive and Watkins Road. Ongoing work on the 3B phase of Project 3 from Robinson Ranch Road to the new roundabout intersection with County Road 209B includes clearing and grubbing for the roadway and pond sites and installing stormwater structures and drainpipes. Crews are working days, and some nights and weekends to complete the realignment of the intersections of CR209B & Sandridge Road with a roundabout. Expect daytime and evening lane closures with flagmen.
- October 28, 2024- Expect daytime and evening lane closures with flagmen beginning November 4 for road work on the 3B phase of Project 3 from Robinson Ranch Road to the new traffic circle intersection with County Road 209B. Work will take approximately 4 months to complete.
- October 11, 2024- Russel Road at CR209B- Crews are beginning traffic circle construction on Russel Road at County Road 209B. Clearing operations started October 11 and crews are installing underground pipes. Anticipate daily lane closures in this area for the duration of the project. Driver should also expect daytime and evening lane closures with flagmen beginning November 1 for road work. Work will take approximately 4 months to complete.
- September 13, 2024- Anticipate intermittent, single-lane closures on County Road 209 (Russell Road) at Watkins Road and Oak Stream Drive for the final work on phase 3A of project 3. Construction is ongoing for the 3B phase of Project 3 from Robinson Ranch Road to the new traffic circle intersection with County Road 209B. Anticipate daily lane closures in this area for the duration of the project. Please slow down and use caution around the crews working close to the roadway. Motorists should expect a 35-mph low-speed zone in the work area.
- August 16, 2024- Anticipate daily, intermittent, single-lane closures on Russell Road at the intersections of Oak Stream Drive and Watkins Road for road work.
- July 26, 2024- Anticipate daily, single-lane closures on Russell Road at the intersections of Oak Stream Drive and Watkins Road for road work. Crews will be paving the roadway at Russel Road, Watkins Road, and Oak Stream Drive July 31 through August 2, weather permitting. Anticipate lane shifts and intermittent lane closures beginning each day at 7 a.m. Work will start on Russell Road at CR 209B and move south to Oak Stream Drive. Expect delays. Anticipate lane shifts and temporary lane closures beginning each day at 7 a.m. Expect delays.
- June 27, 2024- Anticipate daily, single-lane closures on Russell Road at the intersections of Oak Stream Drive and Watkins Road the week of July 29 for road work.
- June 10, 2024- Construction began on June 11 for the 3B phase of Project 3 from Robinson Ranch Road to the new traffic circle intersection with County Road 209B. Anticipate daily lane closures in this area for the duration of the project.
- May 23, 2024- The first layer of pavement is complete at Russell Road and Oak Stream Drive and crews anticipate being able to open the Oak Stream Drive access gate on evenings and weekends beginning on May 24. The gate will remain closed and locked on workdays while the project is underway.
- May 22, 2024- Anticipate daytime, single-lane closures with flaggers beginning May 28th and continuing for up to one week on Russell Road and Watkins Road. Lane closures are also continuing for an extended period on Russell Road and Oak Stream Drive.
- May 7, 2024- Anticipate daytime, single-lane closures with flaggers beginning May 20th and continuing for up to one week on Russell Road from Sandridge Road to County Road 209B. Please slow down and use caution around the crews working close to the roadway.
- April 4, 2024- Anticipate daytime single-lane closures for sidewalk installation on the east side of Russell Road.
- March 28, 2024- Anticipate intermittent lane closures daily for drainage work at Watkins Road.
- March 22, 2024- Crews will be installing drainage pipes at Watkins Road this week. Anticipate single-lane closures and flagging operations on Monday, March 25, from 9 a.m. to 3 p.m.; Tuesday, March 26 from 7 p.m. through Wednesday, March 28 at 6 a.m.; and again, on March 28, from 9 a.m. to 3 p.m.
March 7, 2024- Both travel lanes on Russell Road near Oak Stream drive are open to traffic. - February 29, 2024-Anticipate daytime single-lane closures on Russell Road at the Oak Stream entrance continuing for up to three weeks to expand the shoulder to set up the permanent MOT for the roadway work. Watch for flaggers. Motorists should expect a 35-mph low-speed zone in the work area.
Access to Oak Stream Drive is closed on Russell Road for major road work, drainage, and sidewalk and crosswalk installation. The closure started on February 12. Residents will need to use the Sandridge Road entrance and exit. Emergency crews have full 24/7 access. The contractor has 180 days to complete the entire project in the area, and that entrance will be closed for a portion of that time frame. We'll update our community when it's back open. While this project was under development and again just before starting the field work County staff discussed this closure with emergency responders, the HOA, and the school district to ensure a smooth process before the project began. This current plan was determined to be the best way to get this project done as quickly and safely as possible.
-
February 20, 2024- Daytime lane closures on Russell Road at the Oak Stream entrance area begin on February 26 to expand the shoulder to set up the permanent MOT for the roadway work. Watch for flaggers
-
January 19, 2024-Access to Oak Stream Drive will be closed on Russell Road beginning February 12, for sidewalk and crosswalk installation. Residents will need to use the Sandridge Road entrance and exit. Emergency crews will have full access. The contractor has 180 days to complete the entire project in the area, and that entrance will be closed for a portion of that. We’ll have a concrete time frame in the upcoming days, and we’ll release that to our community.
- January 11, 2024- Motorists should expect single-lane closures and a 35-mph low-speed zone in the work area. Access to Oak Stream Drive will be closed on Russell Road beginning February 12, for sidewalk and crosswalk installation. Residents will need to use the Sandridge Road entrance and exit. Emergency crews will have full access. Work will take up to 180 days to complete.
- January 5, 2024 - Road construction is estimated to begin on February 12. The speed limit will be lowered to 35 mph throughout the work zone. Please slow down and use caution around workers.
- December 15, 2023- Construction on the turn lane at Oak Stream Drive is anticipated to begin in early February. Motorists should expect single-lane closures in the work zone and a temporary closure and detour at Oak Stream Drive for sidewalk and crosswalk installation. Emergency crews will have full access.
- December 1, 2023 - This project will be completed in two phases with utility relocation and other preliminary work beginning in January ahead of the construction of the turn lanes at Watkins Road and Oak Stream Drive, and sidewalk work on the east side of the road. The second phase of construction is anticipated to start in summer 2024 and involves roadway realignment and traffic circle construction at the intersection of CR209B, CR209 (Russell Road), and CR739B (Sandridge Road). Motorists should expect daytime, single-lane closures once work begins.
- November 17, 2023- Construction on the fist phase of the project includes adding turn lanes on County Road 209 at Watkins Road and Oak Stream Drive and sidewalk work. Motorists should expect daytime, single-lane closures once work begins. This phase is anticipated to begin after the first of the year with completion by fall 2024.
- October 13, 2023- Phase one construction includes adding turn lanes on Russell Road at Watkins Road and Oak Stream Drive and sidewalk work. Motorists should expect daytime, single-lane closures once work begins.
County Road 216 (CR315) Bonded Transportation Program Project #6A, (Green Cove Springs/Lake Asbury)
Background
This project involves construction of the eastern section of County Road 216, Cathedral Oak Parkway, from Maryland Avenue to US 17. Future plans for this project will create a 4-lane roadway connection from US 17 to BTP project 6B, connecting to the First Coast Expressway. Permitting and design work is well underway, and crews have completed preliminary utility location work in this area. The road construction start date is yet to be determined.
Latest update
- Update January 13, 2026- The team updated wetland functional scores and submitted the permit documents to the USACOE on December 29th. Plans will be signed and sealed when the permits are issued.
Previous update
- Update December 9, 2025- The team is finalizing updated wetland functional scores this week to submit for ACOE approval. Plans will be signed and sealed when the permits are issued. The government shut down affected the time for the permit approval.
- June 10, 2025- County staff continues to work with the Army Corps of Engineers through the permitting process.
- February 14, 2025- Anticipate daytime, single-lane closures on County Road 315 from Maryland Avenue to U.S. Hwy 17 on February 19 and 20 from 9 AM to 5 PM for preliminary utility location work to prepare for future construction of the eastern section of the County Road 216, Cathedral Oak Parkway First Coast Expressway connector road.
County Road 218, Bonded Transportation Program project #1 (Middleburg)
Background
This project involves reconstructing and widening the 2.7-mile section of roadway from Masters Road to Pine Tree Lane into four lanes, adding a median, turn lane, curbs, gutters, sidewalks, and bike lanes, and resurfacing from Cosmos Avenue to Pine Tree Lane.
The westbound temporary pavement will remain in place until the underground stormwater pipe and utility relocation work is complete. The speed limit is 25 mph throughout the work zone. Please slow down and respect the safety of our workers. Project completion is expected in summer 2026.
- Nighttime road work notice
This project may involve nighttime construction activities to reduce daytime disruptions and complete the work faster. Residents in the area can expect increased noise levels or vibrations from machinery, as well as potential glare from temporary work lights near the site. We appreciate your understanding and patience during this time. Our team will make every effort to minimize inconvenience and complete the work as quickly and safely as possible.
Latest update
- Update February 10, 2026- Work is continuing on the installation of drainage structures, pipes, sub-base, and base materials along the north side of this project. The project schedule is currently under review for possible adjustments.
Previous updates
- Update January 13, 2026- Work is underway on asphalt removal, drainage installation, pipe placement, and driveway demolition along the north side of County Road 218. The project schedule is currently under review for possible adjustments.
- Update January 12, 2026 (Aster Avenue detour, Middleburg) – Anticipate a detour of Aster Avenue on January 14 and 15 for road work. Traffic traveling east and west from County Road 218 to Aster Avenue (North) will be directed to N. Dolphin Avenue, then Yucca Street.
- Update December 9, 2025 — Crews have completed installing drainage structures and pipes, as well as demolishing existing driveways along the south side of the project. They also finished placing the sub-base, curbing, sidewalks, and limestone base, applied tack coat, and laid the first base course of asphalt in this area. Traffic was then shifted onto the newly paved southbound section of the corridor. Work has now moved to the north side, where crews have begun by removing the old asphalt from the roadway.
- Update November 26, 2025- Drivers should expect both travel lanes to shift to the south side of the newly widened roadway beginning the afternoon of November 26. Only the initial layer of asphalt is in place, so watch for bumps near manholes. The speed limit will remain 25 mph throughout the work zone. Please stay alert and drive with caution.
- Update November 13, 2025 - Crews will be paving on the south phase November 24 to November 26. Drivers can expect a traffic switch immediately after that paving operation. Please be patient with our delays during the paving and traffic switch operation.
- Update November 10, 2025- Crews completed lining placement at Pond Site #3 and continued installing drainage structures, pipes, and driveway pavement repairs along the south side of the project area. Work also included sub-base, curbing, sidewalk, and limestone base placement, plus tack coat application. Paving work on County Road 218 is scheduled for the last week of November. Drivers can expect daytime, single-lane closures and flagging operations during the work. The project remains on schedule.
-
Update November 5, 2025- Crews will be working on roadway base completion on County Road 218 the week of November 3. Drivers can expect detours in the area. Paving work on County Road 218 is scheduled for the last week of November. Drivers can expect daytime, single-lane closures and flagging operations during the work.
-
Update October 31, 2025- Crews will be working on roadway base completion on County Road 218 the week of November 3. Drivers can expect detours in the area next week.
- Update October 14, 2025- Crews installed lining material at Pond Site #3 and completed lining at Pond Site #4. Continued work on installing drainage structures and pipes, demolishing existing driveways, and performing pavement repairs along the project's south side. The placement of sub-base, curbing, sidewalks, and limestone base is ongoing in the same area. The project remains on schedule.
- Update October 13, 2025- A road closure and detour for drainage work will continue on Aster Avenue the week of October 13. Access the library from the back. Follow posted detour signs.
-
Update September 18, 2025- South Dolphin Avenue will be closed just south of County Road 218 on Monday, September 22, and Tuesday, September 23, for drainage installation work. Drivers will be detoured on County Road 218, Aster Avenue, and Angora Street during the work. A road closure and detour are also scheduled on Aster Avenue on Wednesday, September 24, through Friday, September 26. Access the library from the back. Follow posted detour signs.
-
Update September 12, 2025- South Dolphin Avenue will be closed just south of County Road 218 on Friday, September 5, and Wednesday, September 10 through Monday, September 15 for drainage installation work. Drivers will be detoured on County Road 218, Aster Avenue, and Angora Street during the work. Follow posted detour signs.
- Update September 9, 2025- Excavation at Pond Site 4 is complete. Crews are installing drainage structures and pipes, demolishing existing driveways, and performing ongoing pavement repairs along the south side of the project. Work also continues on placing sub-base material, curbing, and the limestone base in this area.
- Update August 12, 2025- Excavation at Pond Site #3 is nearly complete, and grass has been installed at Pond Site #4. Current activities include installing drainage structures and pipes, demolishing existing driveways, and repairing pavement for driveways and pipe crossings along the south side of the project. Crews are also working on placing sub-base, curbing, and a limestone base.
- Update July 8, 2025- The project is progressing on schedule. Liner placement is completed on pond site 4, and crews are continuing with the installation of drainage structures and pipes, along with placing subbase, curbing, and the limestone base.
- June 10, 2025- The project remains on schedule for completion. Crews are continuing with drainage structure installation and liner placement for pond site 4. Existing driveway demolition and pavement repairs also continue, along with the placement of subbase, limestone base, and curbing.
- May 13, 2025- Excavation at Pond Site 4 is complete, and liner installation has been finished on Ponds 4 and 2. Drainage structure installation is ongoing, including the demolition of existing driveways, pavement repairs, and the placement of subbase material and curbing. Crews have also started placing the limestone base. The project remains on schedule for completion.
- May 15, 2025- Excavation at Pond Site 4 is complete, and liner installation has been finished on Ponds 4 and 2. Drainage structure installation is ongoing, including the demolition of existing driveways, pavement repairs, and the placement of subbase material and curbing. Crews have also started placing the limestone base. The project remains on schedule for completion.
- April 21, 2025- Anticipate overnight single-lane closures on April 21, from 8 pm to 5 am on April 22 for roadwork. Watch for flaggers.
- April 11, 2025- Pond site excavations are ongoing, and crews are installing drainage structures, removing driveways for pipe work, making pavement repairs, and placing subbase and curbing. Anticipate intermittent, single-lane closures throughout the construction zone.
- March 14, 2025- Crews are continuing with pond site excavations and liner placement, drainage structure installation, driveway demolition, and pavement repairs over pipes and driveways. Anticipate intermittent, single-lane closures throughout the construction zone.
- February 14, 2025- Crews are continuing pond site excavations, installing drainage structures, demolishing existing driveways, and placing asphalt.
- January 3, 2025- Anticipate intermittent, single-lane closures throughout the construction zone.
- August 7, 2024- A traffic shift for both directions of County Road 218 begins overnight on August 7 for utility and drainage work. Please slow down and pay attention to the new traffic pattern.
- July 11, 12024- Anticipate a northerly traffic shift for both directions of County Road 218 beginning August 1 for utility and drainage work.
- June 27, 2024- Anticipate daytime, single-lane closures with flaggers from 7 a.m. to 5:30 p.m. on County Road 218 from Masters Road to Pine Tree Lane beginning July 1 for road work. The speed limit is 35 MPG throughout the work zone. Please slow down and respect the safety of our workers.
- May 16, 2024- Drivers should anticipate a traffic shift and nighttime single-lane closures on the north side of the road for sidewalk and curb placement beginning the week of May 20th.
- April 16, 2024- Drivers should anticipate a traffic shift and single-lane closures on the north side of the road for the next 30 days.
CR218/Spencer Industrial Drive (Clay Hill) – Anticipate intermittent, daytime, single-lane closures with flaggers beginning Monday, June 16, on County Road 218 at Spencer Industrial Drive for intersection improvements and turn lane installation. Work could take up to 260 days to complete. Please slow down and drive with caution in the work area.
Latest update:
- Update February 13, 2026- The project was substantially completed on February 12, with final punchlist items remaining. Traffic cones will remain in place until all work is complete, but the roadway is fully open to traffic.
Previous updates:
- Update January 13, 2026- The Spencer Industrial Drive project remains on schedule. The first asphalt lift for all four lanes is complete, with CR 218 improvements scheduled for paving next month. The project is expected to be completed in early Spring 2026.
- Update December 9, 2025- The project remains on schedule, with CR 218 paving scheduled for next month. The initial asphalt lift for all four lanes was recently completed, and overall project completion is expected in early Spring 2026. Drivers should expect intermittent daytime single-lane closures and flagging operations on weekdays from 7 AM to 4 PM as work continues.
-
Update October 31- Drivers should anticipate intermittent, daytime, single-lane closures and flagging operations weekdays from 7 AM to 4 PM on Spencer Industrial Drive at County Road 218 beginning Wednesday, September 17, for road widening construction work on County Road 218.
- Update July 8, 2025- Construction began on June 16 for intersection improvements and turn lane paving at Spencer Industrial Drive and County Road 218. Current work includes installing erosion control measures, surveying work, and mobilization activities.
County Road 220 Widening and Reconstruction Phase 1 and Phase 2 projects (Middleburg/Lakeside)
Background
Crews began Phase 1 of the lane widening and reconstruction project on County Road 220 the week of December 16, 2024, which includes intersection improvements at Rideout Ferry Road. Phase 2 work, including a new four-lane bridge over Little Black Creek, began on January 20, 2025. Drivers can expect detours that will continue for the duration of the project. All businesses and residents will have full access to their properties. The County worked closely with emergency responders and the school district throughout the planning process. Both phases are expected to be completed in late 2026.
- Nighttime road work notice This project may involve nighttime construction activities to reduce daytime disruptions and complete the work faster. Residents in the area can expect increased noise levels or vibrations from machinery, as well as potential glare from temporary work lights near the site. We appreciate your understanding and patience during this time. Our team will make every effort to minimize inconvenience and complete the work as quickly and safely as possible.
Latest Updates
- Update February 10, 2026- The projects remain on schedule for completion in Summer 2026. A new traffic shift is in place east of Henley Road. Final drainage and curb-and-gutter work continues on westbound CR 220 between Joe Johns Road and Henley Road. The bridge deck is complete, with railing and approach slab work ongoing. Motorists are encouraged to drive safely through construction zones.
Previous updates
- Update January 13, 2025- Work continues on the CR 220 bridge replacement and four-lane widening from Knight Boxx Road to Hollars Place and remains on schedule for completion in Summer 2026. The new bridge deck is expected to be finished within the next two weeks, followed by railing installation and approach slabs. Utility and pipe work between the new bridge and Chief Ridaught Trail is nearly complete. Upcoming pavement tie-ins east of Henley Road will require daytime single-lane closures and may cause delays. Please use caution and drive courteously through construction zones as the project nears completion.
- Update December 17, 2025- Beginning the second week of January, the eastbound right-turn lane on County Road 220 at Henley Road will be closed for construction for approximately 25 days. During this time, eastbound, northbound, and southbound traffic will be reduced to a single lane, and traffic signal timing will be adjusted to help manage traffic flow. Motorists should plan for delays and use alternate routes when possible. Starting January 19, phased paving will occur at the County Road 220/Henley Road intersection for approximately two weeks. All directions will remain open, but expect delays as traffic will be directed by flaggers. School crossings will continue as normal.
- Update December 9, 2025- Work is progressing on the CR 220 widening project from Knight Box Road to Hollars Place, which remains on schedule for completion in Summer 2026. New pavement and a lane shift were recently completed on the west side of Henley Road. Bridge work is also advancing, with the bridge deck nearing completion. This week, crews are scheduled to place new pavement on CR 220 near Joe Johns Road and the bridge replacement area. Please continue to drive safely and courteously through construction zones.
- Update December 5, 2025- Crews will be paving on the County Road 220 bridge December 8-12, 2025. Drivers can expect daytime, single-lane closures and flagging operations.
- Update November 10, 2025- Work is progressing on the CR 220 widening project, spanning from Knight Box Road to Hollars Place. The project remains on schedule for completion in late summer 2026. Crews will be paving the outer lanes of CR 220 just east and west of Henley Road, November 11–14, 2025. Paving work near Joe Johns Road and the bridge replacement area is planned for the second week of December. Drivers are reminded to remain alert and practice safe, courteous driving throughout the construction zones.
- Update November 5, 2025- Daytime paving work is scheduled for November 11- 13, 2025, in the east and westbound lanes of Henley Road. Crews will also be paving on the County Road 220 bridge December 8-12, 2025. Drivers can expect daytime, single-lane closures and flagging operations.
- Update October 28, 2025- From November 10–12, crews will begin the first phase of asphalt paving on County Road 220, west of Henley Road moving east. Drivers can expect daytime lane closures starting at 9:00 AM each day, with flaggers to direct traffic. Drivers should expect delays and consider using alternate routes when possible.
- Update October 14, 2025- Work continues on the CR 220 widening project, from Knight Box Road to Hollars Place.The project is on schedule (completion late summer, 2026), with the first portion of the bridge deck completed. Work will intensify in the Henley Road intersection and the Joe Johns Road areas in the upcoming months. Drivers should expect lane closures and possible delays as the project continues.
- Update October 8, 2025- A County Road 220 traffic shift is planned for Monday, October 20, 2025, west of Henley Road as operations switch to the next phase of the CR220 widening and reconstruction project. Anticipate daily, single-lane closures with flaggers in both directions of Henley Road and County Road 220 for utility work, paving, and sidewalk placement on the north side of County Road 220. Two travel lanes will remain open, and all driveways will be accessible during the work.
- Update September 9, 2025- Work continues on the CR 220 project, from Knight Box Road to Hollars Place. The project is on schedule, with drainage pipe installation continuing along CR 220. Work will intensify in the Henley Road intersection and the Joe Johns Road areas in the upcoming months. Drivers should expect lane closures and possible delays as the project continues.
- Beginning September 8, the westbound lane of County Road 220, west of Henley Road, will be closed overnight on weekdays from 7:00 PM to 5:30 AM for approximately two weeks. Drivers are advised to watch for flaggers and use caution due to limited nighttime visibility.
- Update August 12, 2025- Work on County Road 220 from Knight Boxx Road to Hollars Place at the Henley Road intersection is about 45% complete. The drainage work on Rideout Ferry Road is complete. Drainage work on the east side of Henley Road is ongoing and expected to be completed on schedule. Over half of the new bridge deck has been poured. Work is anticipated to ramp up near the Joe Johns Road intersection with County Road 220. Drivers should expect lane closures and possible delays as the project continues.
- Update July 16, 2025- Starting July 16, northbound Henley Road at County Road 220 will only have one lane open. Additionally, the northbound right through lane will be closed until further notice. Northbound drivers on Henley Road will have one lane at that intersection to travel through. Please drive slowly and carefully through this active construction zone.
- Update July 8, 2025- The old CR 220 bridge has been completely removed, and construction of the new bridge is well underway. Work is anticipated to intensify at the County Road 220 and Henley Road intersection in the coming months. Storm drain and pipe installation at Rideout Ferry Road is near completion.
- Update June 24- Work on Phase 1 and Phase 2 of the CR 220 widening and bridge replacement project is 30% complete, with completion anticipated by late 2026. The first bridge piles are in place, and the old bridge has been removed. Please continue to drive carefully through the construction zone and respect the construction workers.
- Update June 18- Beginning June 23, the right turn lane from Henley Road onto County Road 220 will be closed for construction work. Drivers will be able to make a right turn from the through travel lane.
- May 13, 2025- Work continues on Phase 1 and Phase 2 of the CR 220 widening and bridge replacement project, with completion anticipated by late 2026. The first bridge piles are in place, and the old bridge will be removed in the upcoming weeks. Please continue to drive carefully through the construction zone and respect the construction workers.
Project description
Phase 1- County Road 220 will be widened to four lanes from Hollars Place to west of Henley Road, ending at Chief Ridaught Trail. This project includes intersection improvements at County Road 220 and Henley Road. Henley Road will not be closed during phase 1 work and traffic will continue to flow in both directions. Work began the week of December 16, 2024. Drivers can expect single-lane closures and traffic shifts during the work. Only local traffic will be able to access the road from the south end during the work.
Phase 2 - includes widening County Road 220 to four lanes from east of Chief Ridaught Trail to Knight Boxx Road and a new four-lane bridge over Little Black Creek, along with signal updates at Knight Boxx Road and Blanding Boulevard to ease traffic congestion. Work began on January 20, 2025. Local traffic only. Bridge closure in effect.
CR 220 Phase 2 detour route description
Beginning February 11, drivers heading south on Blanding Boulevard can no longer make a U-turn at the Henley Road intersection to allow more time for drivers heading north on Henley Road to turn right onto Blanding Boulevard. CCSO is enforcing the no U-Turn at this intersection.
- Eastbound traffic along County Road 220 at the Baxley Road intersection will be detoured north on Baxley Road, east on State Road 21, south on Knight Boxx Road, and east on County Road 220 through the left turn lane.
- Westbound traffic on County Road 220 at the Henley Road intersection will be detoured north onto Henley Road through the right turn lane on the northeast corner of the intersection, west onto State Road 21, and south onto Baxley Road to County Road 220.
- Westbound traffic on County Road 220 at the Knight Boxx Road intersection will be detoured north onto Knight Boxx Road, west onto State Road 21, south onto Henley Road, and west onto County Road 220.
- January 28, 2025- Clay Electric will set the utility pole at this intersection on the night of Thursday, January 30. Anticipate nighttime, single-lane closures on Henley Road from 6 PM to 6 AM. Watch for flaggers and expect delays.
- Road construction and intersection improvements at County Road 220 and Rideout Ferry Road began on January 6. Only local traffic will be able to access the road from the south end during the work.
Public Meeting -We collaborated with the engineering firm Eisman and Russo to hold a public meeting. The public had an opportunity to review project plans, view a presentation, and ask questions. County leaders were also be in attendance to help answer questions.
Please refer to the detour map below:
County Road 220 and Town Center Boulevard Resurfacing from US 17 to west of Brookstone Drive (Fleming Island) — Crews will begin resurfacing County Road 220 from U.S. 17 to Arena Road the first week of February. Drivers should expect nighttime lane closures and traffic shifts during construction. Work is anticipated to begin late February to early March and could take up to three weeks to complete.
Latest update:
- Update February 13, 2026- The project contract has been executed, and the pre-construction meeting was held on February 5, 2026. Construction is scheduled to begin late February to early March, with work performed at night. Single-lane closures and delays are expected during nighttime hours. Motorists are urged to slow down and follow all posted signage for safety within the construction zone.
County Road 315/ Cathedral Oak Parkway utility work (Green Cove Springs)- Anticipate daytime, single-lane closures on County Road 315 north to Cathedral Oak Parkway Monday through Saturday, from 9 a.m. to 6 p.m. for gas main installation work. We will update this notice when the work is complete.
Jefferson Avenue closure (Orange Park) - In June the County’s Public Works Department closed off an area on Jefferson Avenue adjacent to Ridgeview Elementary School due to an unsafe subsurface structure. County officials made school leaders aware of the move, which is aimed to prevent vehicles from parking on the stretch. Pedestrian traffic is still permitted.
Live Oak Lane/Old Jennings Road (Middleburg)
Background
This project includes the construction of a new 3.5-mile, 12-foot-wide multi-use trail extending from Live Oak Lane/Old Jennings Road, along Long Bay Road, to the State Road 21 intersection. Work began on April 2 and is expected to be completed in 345 days.
Latest update
- Update February 10, 2026- The project remains on schedule. Utility relocation is complete, and final paving to the FWC checkpoint station is expected in the coming weeks, weather permitting. Please observe the posted 25 mph speed limit on Live Oak Lane, as excessive speeding has been observed. The Clay County Sheriff’s Office has been notified. Motorists are reminded to drive safely.
Previous updates
- Update January 13, 2025- The Live Oak Lane/Greenway Trail project remains on schedule. Roadway paving is complete to just north of the state forest parking area, and base material for the SUNTrail has been placed up to the FWC checkpoint. Final grading will begin once utility relocation is complete. Please observe the 25 mph speed limit on Live Oak Lane and drive safely.
- Update December 9, 2025- The project remains on schedule. The contractor has completed roadway paving up to the trail crossing just north of the state forest entrance. Please remember that the speed limit on Live Oak Lane is 25 mph. Contractors and inspectors have reported excessive speeding, and the Clay County Sheriff’s Office has been notified. Please drive safely.
- Update November 10, 2025- The project is progressing smoothly and remains on schedule. The trail section has been recently paved, and work is ongoing on the dirt road paving portion. The contractor plans to complete paving of the main road up to the Jennings State Forest Visitors Center by Thanksgiving 2025.
- Update October 14, 2025- The project is progressing well and remains on schedule. Base material for the trail has been placed, and Clay Electric has completed most of the utility work. The trail portion of the project was paved recently, and work continues on the dirt road paving portion.
- Update August 12, 2025- The project is progressing well and remains on schedule. Base material for the trail has been placed, and Clay Electric has completed all utility work. Grant funding has been secured for the Sun Trail extension, which will add a 12-foot-wide concrete trail from Live Oak Lane to Blanding Boulevard along Old Jennings Road and Long Bay. Design is 30% complete, with construction expected to begin in the first quarter of 2026.
- Update July 8, 2025- Work on this project is progressing as planned, with utility relocation and road construction currently underway.
-
Update May 13, 2025- Surveying and wetland flagging are complete, a traffic warrant study is in progress at the Warm Springs intersection, and design work is now underway. Minimal traffic impacts are anticipated at this time.
-
Update February 12, 2025- During the February 11 BCC Meeting, Commissioners awarded RFB No. 24/25-008, Greenway Trail and Paving Project to Besch and Smith Civil Group Inc. in the amount of $2.4 million for the construction of the North Florida Greenway Trail running from Live Oak Lane to the entrance to Jennings State Forest and includes the paving of Live Oak Lane. Preliminary utility relocation work is anticipated to begin in a few weeks and all work is expected to be completed in 345 days. This project is partially funded by the Florida Department of Transportation.
- Update September 19, 2024- All right-of-way acquisitions are in place and the County will be moving forward with selecting a roadway contractor and construction will start soon thereafter.
- As of Tuesday, September 3, 2024, Clay County is awaiting the final acquisition of the right-of-way for the Live Oak Lane paving project. One resident has not agreed to the terms of the acquisition. Upon receipt of the final agreement, the County will begin selecting a roadway contractor and the construction will begin soon thereafter.
- October 13, 2023- This project is in the right-of-way acquisition phase. If all adjacent property owners agree to provide the necessary right of way for the installation of the 12-foot paved, multipurpose Sun Trail, road paving and trail installation could begin in spring 2024. If you have any questions about this project, please email askclay@claycountygov.com.
Click on the image below to download the Live Oak Lane Plot Map.
Previous update-
The Clay County Board of County Commissioners is excited to announce that the County has been awarded funding from the State of Florida to make improvements to Live Oak Lane, as requested by numerous Live Oak Lane residents. The improvements authorized by the State include paving the road and the requirement that a sidewalk be installed concurrently with the road paving. To satisfy the State's funding requirements and meet all road and safety standards, the County needs to acquire an additional 20' of each property that runs parallel to Live Oak Lane. The needed 20' is currently within an easement on each property for electrical lines that run along the Live Oak Lane portion of each property.
Betsy Condon, District 4 Commissioner, hosted a public meeting on Thursday, July 13, 2023, at the Middleburg/Clay Hill Library, 2245 Aster Ave, Middleburg, FL, 32068, for the property owners to ask any questions and provide input.
lf you have any questions about this project, please email askclay@claycountygov.com.
Radar Road new construction (Fleming Island)- Crews began preliminary utility relocation work ahead of construction of the new two-lane roadway connecting Radar Road to Town Center Boulevard at the current roundabout, which is expected to begin in early 2026. Once complete, this project will fully connect U.S. 17 to Town Center Boulevard and include bike lanes, curbs and gutters, and drainage features.
Latest update:
- Update February 13, 2026- The pre-construction meeting was held on February 4, 2026. Drainage structures have been ordered, and on-site work is scheduled to begin on March 30. The project duration is 390 days, with substantial completion anticipated at 345 days.
Previous updates:
- Update January 13, 2026- The Radar Road project preliminary utility relocation is nearly complete, with Clay Electric poles moved out of the new roadway. Other utilities will shift overhead lines to the new poles in the coming weeks. The project contract is in its final stages, with a pre-construction meeting planned for February 5, 2026.
Town Center Boulevard Drainage Improvements (Fleming Island) — Completed
Update February 11, 2026- The final inspection was completed on February 11. The contractor is finishing up cleanup work, removing MOT signs, and will reopen the road by 5:00 PM this afternoon. The project was completed 38 days ahead of schedule.
Previous Update:
Drainage improvements are underway just north of Cypress Glen Drive, where crews began replacing a failing 24-inch drainage pipe on January 5, 2026.
The roadway is closed to all traffic between Covington Lane/Heritage Oaks Court and Cypress Glen Drive for the duration of the approximately 45-day project.
Traffic impacts include daytime lane closures, traffic shifts, and sidewalk closures with a clearly marked detour; a temporary sidewalk is now in place. Paving, striping, and sodding work is nearing completion.
Work is coordinated with public safety and the school district to minimize impacts to emergency vehicles and school buses, and the Clay County Sheriff’s Office will monitor traffic on U.S. 17. Motorists should follow posted detours and all traffic control signage.
Walburg Street (Green Cove Springs)- Walburg Street closed on Monday, January 6, 2025, and will remain closed for approximately 12 months during the construction of the new Clay County Economic and Development Services building.
Blanding Boulevard Intersection Improvements from South of Wells Road to the Ortega River (Orange Park)- FDOT began a project to redesign the intersection of Blanding Boulevard (State Road 21) and Wells Road on Monday, August 4.
The project includes milling and resurfacing, base work, shoulder treatment, drainage improvements, curb and gutters, traffic signals, lighting, highway signing, bridges, sidewalks/bicycle path, and other incidental construction. No single lane closures on Blanding Boulevard and Wells Road will be allowed from 6 a.m. to 8 p.m. No double lane closures on Blanding Boulevard and Wells Road will be allowed from 5 a.m. to 10 p.m. The $8 million project is estimated for completion in summer 2026, weather and unforeseen circumstances permitting. Drivers should expect lane closures and possible delays as the project continues.
- Nighttime lane closures Monday through Thursday from 8 p.m. to 6 a.m. for road work.
Latest updates
- Update February 10, 2026- Work is ongoing, with signal pole installations and lane shifts in progress. The project is scheduled for completion in Summer 2026.
- Update January 13, 2026- Work continues with signal pole installations and lane shifts underway. The project remains on schedule for completion in Summer 2026. The Orange Park Northway resurfacing project will begin the week of January 15, 2026, and is expected to take 4–5 days.
- Update December 9, 2025- Work continues on the project with signal pole installations and lane shifts in progress.Scheduled project completion is summer 2026.The Orange Park Northway resurfacing project will begin the week of December 15, 2025, and should be complete in 4-5 days.
- Update November 10, 2025- Work continues on the project with utility locates and signal pole installations in progress. Drivers should expect lane closures and possible delays as the project continues.
I-295 at U.S. 17 Interchange Improvements (Orange Park)- This project consists of milling and resurfacing, reconstruction, base work, shoulder treatment, drainage improvements, curb and gutters, traffic signals, lighting, highway signing, guardrail, sidewalks, gravity wall, concrete slope pavement, ITS, and other incidental construction on I-295 at U.S. 17 (State Road 15) from south of Wells Road to Collins Road in Clay and Duval counties.
View the FDOT North Florida road and lane closure report at http://www.NFLRoads.com/trafficreport
No anticipated traffic impacts this week.
Previous updates:
FDOT Update Sept. 5- As part of interchange improvements at I-295 and U.S. 17, the traffic signals and roadway striping at U.S. 17 and Wells Road will be placed into their final configuration overnight Sunday, Sept. 7. Once these changes are implemented, roadway striping on eastbound Wells Road will provide for one left turn lane onto northbound U.S. 17, one through lane across U.S. 17 and one right turn lane onto southbound U.S. 17. Drivers are urged to use additional caution in the area as they become familiar with the new configuration. Superior Construction is expected to complete the $30.5 million interchange improvements and resurfacing project by fall 2025, weather and unforeseen circumstances permitting.
State Road 16 resurfacing project (Green Cove Springs/Penney Farms) - Construction is scheduled to begin the week of January 5, 2026, on a project to resurface State Road 16 from State Road 21 to U.S. 17 (State Road 15).
Anderson Columbia Co., Inc. was awarded the contract to complete this $10 million project, which includes milling and resurfacing, base work, shoulder and driveway treatment, drainage improvements and utility adjustments, curb and gutters, sidewalks, highway signing, guardrail, signalization, and other incidental construction.
Traffic is being maintained in accordance with FDOT design standards throughout the project. No lane closures are allowed from 6 a.m. to 7 p.m. Monday through Sunday. No lane closures are allowed from 5:30 a.m. to 8 p.m. within 600 feet of a signalized intersection. On school days within 600 feet of a school zone, no lane closures are allowed from one hour before school begins to 30 minutes after school begins and one hour before school ends to 30 minutes after school ends.
Completion is expected in late 2026, weather and unforeseen circumstances permitting.
Latest update:
- Update February 10, 2026- Work on the project began January 5, 2026, with traffic maintenance, tree trimming, and signage installation. Milling and resurfacing are scheduled from early April through October, with lane closures limited to nighttime operations, except for daytime work from CR 218 to SR 21 as requested by the contractor. FDOT will coordinate schedules and closures with Clay County around the Clay County Fair and other events. Signal pole installations and lane shifts are ongoing, with project completion expected in Summer 2026, weather permitting.
Previous update:
- Update January 13, 2026- Early work on the State Road 16 resurfacing project from SR 21 to U.S. 17 includes traffic control, tree trimming, and signage installation, with milling and resurfacing scheduled from April through October. All lane closures will occur at night, with traffic maintained per FDOT standards.
U.S. 17 (SR 15) Roadway Improvements – Oak Street to Black Creek Bridge (Green Cove Springs)
FDOT began a $12.2 million roadway improvement and resurfacing project on U.S. 17 (State Road 15) from Oak Street to Black Creek in Green Cove Springs on Monday, September 29. Drivers can expect most construction operations to take place between 8 p.m. and 6 a.m. Sunday through Thursday. Intermittent construction operations can be expected during daytime hours between 7 a.m. and 3:30 p.m. Monday through Friday.
- Nighttime lane closures Sunday through Thursday from 6:30 p.m. to 6 a.m. for road work.
Latest update:
- Update February 10, 2026- Work has resumed on the project, with milling and resurfacing continuing on the southbound lane from CR 209 to just north of the Green Cove Springs city limits. Single-lane closures and delays are expected during nighttime hours, as all work requiring lane closures will be performed at night.
Previous update:
- Update January 13, 2026- Work has resumed on the Black Creek Bridge to Oak Street project, with milling and resurfacing underway on the southbound lane from CR 209 to just north of the Green Cove Springs city limits. Single-lane closures and nighttime delays are expected, as all lane-closure work will occur at night.
Background:
The project is designed to enhance traffic flow and reduce congestion, particularly for northbound traffic, and was developed in coordination with the City of Green Cove Springs as part of its Downtown Improvement Plan.
Key improvements include intersection upgrades at CR 209 (Russell Road), such as replacing the existing traffic signal, installing a new signal at Mahama Bluff Road, adding directional median islands, lengthening the northbound left-turn lane on U.S. 17, and improving roadway lighting. The project also includes modifying the median at Boivin Road and CR 209 by converting the full median opening into a directional median, allowing only southbound-to-eastbound turning movements from U.S. 17 to CR 209.
These enhancements will be coordinated with Clay County’s CR 209 widening project, which is currently in its early construction phase. Construction is expected to be completed by late 2026.
U.S. 17 (S.R. 15) from Eagle Harbor Parkway to Water Oak Lane to (Fleming Island) – This FDOT resurfacing and intersection improvement project includes median installation from Water Oak Lane to Village Square Parkway; adding a second travel lane for through traffic on Bald Eagle Road westbound to C.R. 220; adding a median island and two right turn slip lanes from U.S. 17 southbound to C.R. 220 westbound and installing sidewalk and crosswalk improvements; widening and adding second left turn lane from U.S. 17 northbound to East-West Parkway westbound and installing crosswalk and pedestrian signage improvements; widening and extending left and right turn lanes on U.S. 17 southbound at Eagle Harbor Parkway and adding a fourth travel lane for through traffic on U.S. 17 southbound. This project will be mostly completed at night. Drivers should expect lane closures and possible delays as the project continues.
View the FDOT North Florida road and lane closure report at http://www.NFLRoads.com/trafficreport.
- Nighttime lane closures Sunday through Thursday from 7 p.m. to 6 a.m. for road work.
Latest update:
- Update January 13, 2026- Despite the contractor’s best efforts to complete the friction course on US 17 (Water Oak Lane to Eagle Harbor Parkway), colder nighttime temperatures have halted paving operations. Work is expected to resume in Spring 2026, when seasonal conditions are favorable.
Previous update:
- Update December 9, 2025- Despite the contractor’s best efforts to complete the friction course on US 17 (Water Oak Lane to Eagle Harbor Parkway), colder nighttime temperatures have halted paving operations. Work is expected to resume in Spring 2026, when seasonal conditions are favorable. In the meantime, the contractor is reallocating resources to the Green Cove Springs project (Black Creek to Oak Street), where paving activities are scheduled to begin the week of December 8. This project allows for daytime lane closures, when temperature ranges are suitable for paving.
- Update November 10, 2025- The final asphalt paving lift is currently underway on the project from Eagle Harbor Parkway to Water Oak Lane. Drivers should be aware of new traffic patterns at CR 220/Bald Eagle Road and US 17, and exercise extra caution, especially when traveling westbound. A new westbound traffic pattern is also in place at Water Oak Lane—please drive carefully and follow the updated pavement markings.
FDOT First Coast Expressway South -State Road 23 from north of S.R. 16 to east of C.R. 209 (Green Cove Springs) - Construct 9.7 miles of new multi-lane, limited-access, toll road with drainage system, stormwater ponds, traffic signals, lighting, signage, guardrails, 15 new bridges, and two tolling facilities. Construction on this $180 million project began in April 2019 and is expected to be completed in mid- 2026.
View the FDOT North Florida road and lane closure report at http://www.NFLRoads.com/trafficreport.
- No anticipated traffic impacts this week
Latest update: December 17, 2025
Delays, Ramp Closures Expected This Week at First Coast Expressway and State Road 16 Interchange
To accommodate paving operations, evening and early morning delays are expected at the State Road 16/First Coast Expressway interchange Wednesday, Dec. 17 through Friday, Dec. 19.
Delays will occur in both directions of State Road 16 at the First Coast Expressway from 7:30 to 8 p.m. each evening as well as from 4:30 to 6:30 a.m. each morning. During overnight paving operations, the exit from southbound First Coast Expressway to State Road 16 will also close intermittently. Portable message boards on the First Coast Expressway will indicate to motorists when the ramp closure is in place.
Previous updates:
FDOT update August 8, 2025- First Coast Expressway to Open Saturday, Aug. 9 from Blanding Boulevard to U.S. 17
To alleviate congestion for commuters in Clay County, the Florida Department of Transportation will open a newly constructed segment of the First Coast Expressway (State Road 23) from Blanding Boulevard (State Road 21) to U.S. 17 on Saturday, Aug. 9.
Once open to traffic, the First Coast Expressway will help alleviate daily congestion on major roadways, including Blanding Boulevard, U.S. 17, State Road 16, County Road 220, Henley Road, Sandridge Road, Russell Road, and County Road 218. Approximately 5,000 to 8,000 daily trips will be diverted from these routes, easing strain on local infrastructure. Additionally, first responders will gain faster, more direct access to communities, improving response times and accelerating critical care delivery.
Because construction on the First Coast Expressway from north of State Road 16 to east of County Road 209 is not yet complete, some ramps will remain closed to traffic at this time, as shown in the graphic below.
Toll collection on the newly opened segment of the First Coast Expressway is expected to begin Sept. 15, 2025. Drivers can pay tolls using SunPass, another interoperable transponder, or TOLL-BY-PLATE. Toll rates for the First Coast Expressway are established by Florida’s Turnpike Enterprise and are available at www.FirstCoastExpressway.com.
The SunPass Prepaid Toll Program offers the lowest toll rates in Florida, resulting in an average savings of 25% compared to TOLL-BY-PLATE. To learn more about SunPass, please visit www.SunPass.com or call 1-888-TOLL-FLA (1-888-865-5352).
The Clay County segment of the First Coast Expressway includes construction of new roadway from Blanding Boulevard in Middleburg running south and then east through Green Cove Springs and includes a new bridge over Black Creek. This segment is divided into a north project (north of State Road 21 to north of State Road 16) and a south project (north of State Road 16 to east of County Road 209). Sacyr Construction began construction on the $229 million north project in winter 2019 and is expected to complete the project by fall 2025. Superior Construction began work on the $180 million south project in spring 2019 and is expected to complete the project in mid-2026.
Previous update
As part of First Coast Expressway construction, the planned traffic shift at the State Road 16/First Coast Expressway interchange is planned overnight on Wednesday, June 18. When completed, the shift will move the interchange into its final configuration as a diverging diamond interchange (DDI). One through lane will be open in each direction on State Road 16.
The diverging diamond interchange is pictured here.
All ramps at the interchange will remain closed until this segment of the First Coast Expressway is opened to traffic, which FDOT anticipates to be this summer.
- The Florida Department of Transportation is closely monitoring traffic conditions at the new Diverging Diamond Interchange (DDI) at State Road 16 and the First Coast Expressway. While the new configuration is in place, peak-hour congestion remains a challenge due to high traffic volume and on-ramps that are not yet open. FDOT is evaluating potential signal timing adjustments to help improve traffic flow during these busy periods.
From FDOT: A diverging diamond interchange (DDI) is an interchange design in which the two directions of traffic on State Road 16 below the First Coast Expressway will briefly drive on the opposite side of the road. This intersection design creates significant improvements in safety, since long left turns crossing traffic lanes are eliminated and potential conflict points are reduced to 14 from the 26 found in traditional interchange designs.
Additionally, the DDI promotes efficiency with only two clearance intervals (the time for traffic signals to change from green to yellow to red) instead of the six or more found in other interchange designs. The DDI at State Road 16 will join the DDI at Henley Road and First Coast Expressway as the first of this kind in Clay County.
FDOT First Coast Expressway New St. Johns River Bridge (Green Cove Springs) – Work is underway on the third and final segment of the FCE, which includes a new four-lane bridge over the St. Johns River just south of where the Shands Bridge currently stands. The vertical clearance height of the new bridge will be 65 feet from the water line, compared to the existing 45 feet of clearance. The $595 million project starts in 2023 with expected completion in 2030.
Latest update:
FDOT update Jan 6, 2026- An extended closure of the Shands Bridge (State Road 16) is planned this weekend for routine bridge maintenance. The bridge will close at 9 p.m. Friday, Jan. 9, and reopen by 4 a.m. Monday, Jan. 12. If an additional weekend is needed to complete the work, the same closure will be in place Friday, Jan. 16, through Monday, Jan. 19. During the closure, drivers should use the Buckman Bridge as a detour and plan additional time to reach their destinations. In conjunction with the bridge maintenance operation, project teams will also be completing accelerated paving work on Leonard C. Taylor Parkway (State Road 16) between MOBRO Marine and the Shands Bridge. Single lane closures will be in place in this area throughout the weekend, with access to residences and businesses in this area managed by a traffic flagger.
Previous update:
The first delivery of concrete piles for the new Shands Bridge floated down the St. Johns River on Thursday, Feb. 20. Thirteen 30-inch square piles traveled via barge from Gate Precast in Jacksonville to the First Coast Expressway construction site in Green Cove Springs. Deliveries from the facility will continue for the next several years, in addition to 60-inch cylinder piles being manufactured at Standard Precast in Savannah, Ga. In total, 924 concrete piles will be used to construct the new bridge just south of the existing Shands Bridge.
The joint venture team of Johnson Bros. Corporation and American Bridge was selected to complete the design-build project at a cost of approximately $595 million. Work began in November 2022 with completion estimated in 2030, weather and unforeseen circumstances permitting.
Highlights of the 9,300-foot bridge include
- Two 12-foot wide travel lanes in each direction
- 12-foot wide outside shoulders
- 12-foot, 8.5-inch wide shared use path on the northbound side of the bridge to accommodate pedestrians and bicyclists
- 65-foot vertical clearance to enhance opportunities for marine commerce in the region
- 70 mph speed limit
The bridge is a key component of the larger First Coast Expressway project, a 46-mile limited-access toll road that will cross parts of Duval, Clay and St. Johns counties. The First Coast Expressway will reduce congestion on other major roadways in the region, providing new options for daily commuters while delivering additional capacity for storm-related evacuations and other emergencies. More information about the project is available at www.firstcoastexpressway.com.
U.S. 301 two miles south of Normandy Boulevard (Clay Hill/Maxville) - New asphalt test road sections are planned for installation on southbound U.S. 301, approximately two miles south of Normandy Boulevard, on Monday, Oct. 6, 2025. The installation will be completed by Friday, Nov. 14, weather and unforeseen circumstances permitting. During installation, a single lane closure of the outside lane of southbound U.S. 301 will occur. The lane will be closed for approximately one-half mile.
- U.S. 301 (State Road 200) from Northwest 265th Street to State Road 228 (Clay Hill)- Daytime lane closures Monday through February 21 from 9 a.m. to 7 p.m. for road work.
- U.S. 301 (State Road 200) at County Road 218 (Maxville)- Daytime southbound lane closures Tuesday and Wednesday, and northbound lane closure Thursday from 9 a.m. to 3 p.m. for road work.
- U.S. 301 (State Road 200) from County Road 218 to I-10 (Maxville)- Daytime lane closures Monday through February 21 from 9 a.m. to 7 p.m. for road work.
Latest update:
FDOT Update November 10, 2025- FDOT announced that drivers along US 301 should expect lane shifts and possible delays as the Pavement Testing Site adjusts test lane locations in the upcoming months.
Background
The purpose of the asphalt test road is to provide insight into FDOT’s current asphalt pavement design practices and study the performance of new pavement marking materials to improve future design of state roadways. Drivers who access the asphalt test road will be helping to improve sustainability and longevity in Florida’s road infrastructure planning processes by supplementing real-driver data.
