Project #4- CR 739B (Sandridge Road) from Henley Road to west of CR 209 (Russell Road) in Lake Asbury

Print
Share & Bookmark, Press Enter to show all options, press Tab go to next option

Subscribe to receive updates on the Sandridge Road (CR 739B) improvement project

Design and reconstruct the existing two-lane urban roadway into a three-lane roadway on CR 739B (Sandridge Road) from Henley Road to just west of CR 209.

  • Includes a turn lane, curb and gutter, sidewalks, and bike lanes
  • Construction began in summer 2023
  • Estimated completion in summer 2025
  • Budget: $33 million
Map of the Sandridge Road (CR 739B) roadway improvement project from Henley Road to CR 209.