Road and Lane Closures

Post Date:10/14/2019 7:00 AM

October 14-20

Ongoing County Projects

Biloxi Trail

Daytime lane closures for storm system / drainage improvements. Project to begin approximately Sept 30. Approximately 180 days to complete. 

Bottom Ridge

County drainage and utility improvement project. Daytime single lane closures. Project is expected to go through March 2020.

Cheswick Oak Avenue and Spencer Plantation Boulevard

Intermittent lane closures for utility installation on Monday, October 14 through Friday October 18, 2019, between 7:00 a.m. and 4:30 p.m.

Dover Bluff Drive

Daytime lane closures for storm system / drainage improvements. Approximately 180 days to complete project.

Indigo Avenue Road Improvements

Work location from Cosmos Avenue to Mayflower Street. County road project involves existing dirt road and paving. Anticipate daytime single lane closures. Job began on September 3 and is estimated to take 90 days.

Lester Murray Lane, Spicewood Circle West, and Evergreen Lane

Single lane closures for utility upgrades on the week of October 14 through 18, 2019 between 7:00 a.m. and 4:30 p.m.

Thunderbolt Road Park

Contractor is on site for a Parks Department project. Anticipate construction traffic on Thunderbolt Road. 

 

FDOT Projects

County Road 315 south of Green Cove Springs                    

Nighttime lane closures weeknights from 7 p.m. to 5 a.m. for road work

Kingsley Avenue at McIntosh Avenue

Nighttime lane closures Thursday from 9 p.m. to 6 a.m. for utility work.

Sandridge Road from SR 23 to Rolling View Blvd.                        

Daytime lane closures with flaggers weekdays from 7 a.m. to 5:30 p.m. for road work.             

State Road 21 Over South Prong Black Creek

Daytime lane closures Saturday, October 5, from 8 a.m. to 8 p.m. for bridge replacement. The new bridge is on the east side of the existing bridge. North and southbound traffic will continue on existing bridge during construction.                                                                                                                                                    

US 17 From Black Creek Bridge to Hibernia Road

Daytime lane closures weekdays from 9 a.m. to 5:30 p.m. for road work.                                            

No lane closures will be permitted weekdays between 5:30 a.m. and 9 a.m. No lane closures will be permitted within 600 feet of the signal at Fleming Plantation Boulevard between 5:30 a.m. and 8 p.m. seven days a week. The current posted speed limit of 55 miles per hour will be maintained throughout construction.

U.S. 17 south of Green Cove Springs

Daytime lane closures weekdays from 8:30 a.m. to 4:30 p.m. for road work.

U.S. 17 from Warner Road to Crews Road

Daytime northbound lane closures weekdays from 9 a.m. to 3:30 p.m. to construct a turn lane.

 

First Coast Expressway Work

US 17

Location is south of Green Cove Springs. Anticipate north and southbound daytime inside lane closures October 7 through 11, 2019, from 8:30 a.m. to 4:30 p.m.

Sandridge Road

Location between Rolling Hills and Cross Creek Subdivisions. Temporary lane closures Monday through Friday from 7:00 a.m. to 5:30 p.m.  Contractor will use flagmen at all times.

Henley Road

Location between Caleb Court and Lake Asbury Road.  Contractor is working in Phase 1 of the roadwork, during which time, all four lanes of traffic will be open. Sidewalks will remain open for the duration of the entire project.

CR 315 (Springbank Road)

Nighttime inside lane closures north and southbound from 7:00 p.m. to 5:00 a.m. October 7-11, 2019.