Phase 2 of County Road 220 project to begin on January 20

Work will take about 16 months to complete.

Post Date:01/08/2025 1:00 PM

Crews will begin Phase 2 of the lane-widening and reconstruction project on County Road 220 on Monday, January 20, 2025.

All businesses and residents will have full access to their properties.

Phase 2 includes widening County Road 220 to four lanes from east of Chief Ridaught Trail to Knight Boxx Road and a new four-lane bridge over Little Black Creek, along with signal updates at Knight Boxx Road and Blanding Boulevard to ease traffic congestion. Work will begin on January 20 and will take about 16 months to complete.

The County worked closely with emergency responders and the school district throughout the planning process.

CR 220 Phase 2 detour route description

Eastbound traffic along County Road 220 at the Baxley Road intersection will be detoured north on Baxley Road, east on State Road 21, south on Knight Boxx Road, and east on County Road 220 through the left turn lane.

Westbound traffic on County Road 220 at the Henley Road intersection will be detoured north onto Henley Road through the right turn lane on the northeast corner of the intersection, west onto State Road 21, and south onto Baxley Road to County Road 220.

Westbound traffic on County Road 220 at the Knight Boxx Road intersection will be detoured north onto Knight Boxx Road, west onto State Road 21, south onto Henley Road, and west onto County Road 220.

You can view those detours on the map below:

Detours for CR-220 Widening Phase 1 and Phase 2

If you have questions about this project, please email askclay@claycountygov.com.